ESKOM’S LOAD REDUCTION SCHEDULE FOR OCTOBER 2024

Load Reduction in Ivory Park

Load Reduction in Ivory Park

Illegal connections and electricity theft burdens transformer load. While loadshedding remains suspended, Eskom implements load reduction from 05:00 – 09:00 and 17:00 – 22:00.

In KAE areas affected include: Ivory Park Extension 3, 8, 9, 10; Rabie Ridge; Kaalfontein Extension 1, 2 & 5 and Ebony Park Ext 1. The areas will be affected as follows:

DAYDATETIME
Tuesday01 October 202417:00 until 22:00
Friday04 October 202417:00 until 22:00
Monday07 October 202405:00 until 09:00
Sunday13 October 202405:00 until 09:00
Thursday17 October 202405:00 until 09:00
Thursday24 October 202417:00 until 22:00
Saturday26 October 202405:00 until 09:00
October Load Reduction schedule affecting the areas of Ivory Park, Rabie Ridge, Ebony Park and Kaalfontein