LOADSHEDDING SCHEDULE FOR THE WEEK

“Stage 4 loadshedding will be implemented from 12:00 on Sunday until 05:00 on Monday.
Loadshedding will then vary between Stages 4 and 3 until Wednesday morning.” said Eskom in a statement on Sunday.

Our areas of Kaalfontein, Allandale, Ebony Park (KAE) and surrounding areas of Ivory Park, Rabie Ridge, President Park, Glen Austin, Mayibuye, Klipfontein and Tswelopele will be affected by the loadshedding as follows:

Sunday, 23 October 18:00 until 20:30
Monday, 24 October 02:00 until 04:30
Monday, 24 October 10:00 until 12:30
Monday, 24 October 18:00 until 20:30
Tuesday, 25 October 00:00 until 02:30
Tuesday, 25 October 08:00 until 10:30
Tuesday, 25 October 16:00 until 18:30
Wednesday, 26 October 00:00 until 02:30
Wednesday, 26 October 08:00 until 10:30
Wednesday, 26 October 16:00 until 18:30

Thursday and Friday schedule times will be confirmed during the week. KAE News will update regarding the schedule.