UPDATED LOADSHEDDING SCHEDULE

“Stage 3 loadshedding will be implemented at 05:00 until 16:00 on Wednesday and Thursday. Between 16:00 and 00:00 on both days loadshedding will be implemented at Stage 4,” said Eskom in a statement.

“Eskom anticipates lower stages of loadshedding to be implemented through the weekend as some units return to service” added Eskom.

Our areas of Kaalfontein, Allandale, Ebony Park (KAE), Ivory Park, Rabie Ridge, President Park, Glen Austin, Mayibuye, Klipfontein and Tswelopele will be affected by the Loadshedding as follows:

Wednesday, 13 July 14:00 until 16:30
Wednesday, 13 July 22:00 until 00:30
Thursday, 14 July 06:00 until 08:30
Thursday, 14 July 16:00 until 16:30
Thursday, 14 July 22:00 until 00:00
Friday, 15 July 06:00 until 08:30
Friday, 15 July 14:00 until 16:30
Saturday, 16 July 07:00 until 08:30
Saturday, 16 July 14:00 until 16:30
Saturday, 16 July 22:00 until 00:30
Sunday, 17 July 20:00 until 22:30

Wednesday and Thursday loadshedding stages are confirmed. The stage of loadshedding for the rest of the week is dependent on returning generating units to service and will be confirmed closer to the time.

KAE News will continue giving you updates should the power utility announce further changes to the above schedule.

About Author

Leave a Reply

Your email address will not be published. Required fields are marked *